Tuesday, 6 August 2013

Northern Line Extension: construction shafts cancelled at Radcot Street and Harmsworth Street

Transport for London have let us know that they have decided it is possible to construct the Northern Line Extension without digging shafts at Radcot Street and Harmsworth Street. This is excellent news - the shafts would have caused major disruption in those streets and the streets around them.

Their alternative construction method will be to dig two 'gallery tunnels' separate from the main tunnel, from which ground stabilisation work will take place. When construction is finished the gallery tunnels will be filled in. The gallery tunnels will be dug from the permanent shafts at Kennington Green and Kennington Park - it will mean a slightly longer construction period at these sites.

This is great news for the streets around the temporary construction shafts, but Lambeth will be continuing to push TfL to minimise disruption, reduce noise from construction and the trains, and agree the best possible plans for reinstating Kennington Green and Kennington Park.

 
Email from TfL:

I am writing further to our recent application for a Transport and Works Act Order (TWAO) and the expiry of the representation period to update you that the Secretary of State for Transport has made a decision to hold a public inquiry to consider our application (see footnotes for details of the process) and to advise you of some amendments we have made to the proposals for the Northern line extension (NLE).

These changes have been made in response to consultation feedback, following further engagement with the local authorities of Southwark and Lambeth and the completion of further engineering feasibility work.

The TWAO application includes powers for two potential construction methods (via underground ‘gallery’ tunnels or temporary surface shafts at Harmsworth Street and Radcot Street) to connect the old tunnels to the new NLE tunnels and to stabilise the ground.  Both of these have been assessed in the Environmental Statement (ES).

Following further feasibility work, a decision has been taken by TfL to remove the temporary shafts proposed at Harmsworth Street and Radcot Street on the basis they are no longer required.  This means that no above ground works will be undertaken at either of these locations and construction works will be progressed from the proposed worksites at Kennington Park and Kennington Green instead. The impacts of this change have already been assessed and reflected in the ES.

Factsheet A:connecting the extension to the existing Northern line and stabilising the ground, provides more information about the gallery tunnel construction approach.

Consultation in autumn 2012 on the proposals for a permanent shaft and head house at Kennington Park demonstrated some support for the inclusion of a new community building adjacent to the proposed head house.

Following discussions with Lambeth, TfL has agreed to remove the community building from the scheme on the basis Lambeth would prefer to support existing community facilities in the surrounding area. TfL will amend its proposals for the area by increasing landscaping in the part of the park which was previously taken up by the community building.

With regard to the bee keeping and other community activities carried out by Bee Urban at the Old Lodge site, Lambeth and Friends of Kennington Park are in discussion with Bee Urban about agreeing a new site elsewhere in the park.  This would provide facilities for Bee Urban on a more permanent basis irrespective of permission being granted to build the NLE and in advance of the start of construction.  It would also avoid Bee Urban having to move twice.

The changes to the scheme set out above will be reflected in an addendum to the NLE TWAO environmental statement which is intended to be submitted to the Secretary of State for Transport on 27 August 2013. In line with the TWAO process, the addendum will be subject to a further six week representation period where comments can be made to the Secretary of State for Transport.  We will contact you again with details of where the document can be viewed and how to make a representation.

Yours sincerely

Richard de Cani
Transport for London


Next steps

The Secretary of State announced on 16 July 2013 that a public inquiry will be held to consider our application.  This is likely to start this autumn.

Those who have objected to the scheme should have been notified of this decision by the Department for Transport and asked if they would like to take their representations and comments further and present evidence verbally at the inquiry.  If this is something you would like to do, you will be asked to provide a written statement (statement of case) to outline the full details of the case that you want to present to the inquiry.  This should be received by the Secretary of State and TfL within six weeks of the announcement of the inquiry (so by 27 August 2013).

As the applicant, TfL will also be required to submit a statement of case.

Saturday, 20 July 2013

Northern Line Extension: drop in event for Kennington Green and 373 Kennington Road

Drop in event to consider proposals for a permanent shaft and head house at Kennington Green and an alternative location at 373 Kennington Road

Date: Thursday 25 July

Place: Durning Library
167 Kennington Lane
SE11 4HF

Time:  3.30pm – 8pm

TfL recently submitted an application to the Secretary of State for Transport for a Transport and Works Act Order (TWAO) to build and operate an extension of the Northern line to Nine Elms and Battersea. Theit submission marked the beginning of a statutory consultation period which closed on 18 June 2013.

Their submission includes proposals for a permanent shaft at Kennington Green to allow air in and out of the proposed new northbound underground tunnel, to help cool the tube and extract smoke in the unlikely event of an emergency.  The shaft itself will be located underground in the green, but an above ground structure is required (known as a head house) to house maintenance equipment and vents for the shaft.  This would be located at the corner of Montford Place and Kennington Road within the Beefeater Distillery site. Full details of the proposals are available to view attfl.gov.uk/nle.

Some responses to the consultation put forward an alternative location for the shaft and head house at 373 Kennington Road.  This site is currently occupied by an artist run space called Space Station 65, comprising offices and studios for creative industries and borders with properties on Aulton Place and 377 Kennington Road.

This event will address in detail some of the key issues raised specific to the Kennington Green site, consider the alternative proposals put forward for 373 Kennington Road and provide a platform for further dialogue and discussion.  Senior representatives from the NLE project team will be in attendance on the day.

Wednesday, 10 April 2013

View designs for the Northern Line head house and community building at the old lodge site in Kennington Park


TfL would like to invite you to view the designs for the head house and community building proposed to replace the old lodge site on the corner of Kennington Park Place and St Agnes Place.

Date: Wednesday 17 April 2013
Time: 15:00 – 19:30
Venue: Cafe in the Park, Kennington Park

The designs form part of the wider proposals to extend the Northern line to Nine Elms and Battersea.  They have been developed following engagement with local resident groups and conservation and heritage experts and wider public consultation as part of the Northern line extension (NLE) consultation in autumn 2012.  Further engagement with representatives from local resident and interest groups has helped to refine the designs.

A permanent shaft is required at Kennington Park to allow air in and out of the proposed new southbound underground tunnel, to help cool the tube and extract smoke in the unlikely event of an emergency.  The shaft itself will be located underground in the park, but an above ground structure is required (known as a head house) to house maintenance equipment and vents for the shaft.  This would be located at the site of the old lodge, a small area at the corner of the park.  The proposal is to replace the existing building with the head house required to build and operate the NLE and, in response to consultation, a community building that will provide facilities for local park related use.  There will be no permanent loss of park land as a result of these proposals.

Visuals of the proposals will be on display and members from the NLE team will be on hand to answer questions.

The proposals will be included in TfL's application at the end of April for a Transport and Works Act Order for permission to build and operate the NLE.  Full details of the proposals will be available at tfl.gov.uk/nle and at a number of drop in events and libraries along the proposed route.

Monday, 25 February 2013

Funding the Northern Line Extension


After years of consultations and negotiations there is now agreement between the Government, Mayor of London, Lambeth Council and Wandsworth Council on how the Northern Line Extension should be funded, and we are near the point when Transport for London will start the planning process for the Northern Line Extension.

When the Northern Line Extension was first identified as the preferred transport solution, we as councillors shared the concern of residents that Lambeth shouldn't be paying for it at the expense of Lambeth residents. We have negotiated down Lambeth's contribution to the NLE from 62% to 15% of the monies due from the private developers. This is a huge win for Lambeth and one your Labour councillors have pushed for from the start.

More detail is outlined below but the next step for us all is to work out how we as a community decide how the remaining developer money is used to support the needs of existing communities alongside measures to mitigate the various developments.


Funding the Northern Line Extension

  • The Government will set up an Enterprise Zone – where business rates from the new businesses created as part of the Vauxhall- Nine Elms- Battersea developments will be collected over the next 25 years to pay for the NLE. The only sites in Lambeth in the Enterprise Zone will be the Wandsworth Road Sainsbury’s site and the Vauxhall Square site (immediately south of Vauxhall Cross, bordered by Parry Street, Wandsworth Road and Bondway). All the other sites in the EZ will be in Wandsworth.
  • Funding from the private developers will also contribute to the NLE. This is currently collected through Section 106, in the future this will be collected through the Community Infrastructure Levy. Current estimated development income for Lambeth Council will total £46m, of which the GLA is seeking agreement that £7.3m be allocated to contribute towards the cost of the NLE. This is just 15% of the income we will collect from developers. The rest will be used to pay for the other infrastructure needed in Vauxhall, such as sorting out the Vauxhall Cross gyratory, improved public space and school places. By contrast, the developers of Battersea Power Station will contribute £203m to the NLE.
  • The Government in underwriting the cost of the project, and the risk will lie with the Greater London Authority. Neither Lambeth nor Wandsworth will shoulder any risk. TfL has also committed to taking all of the risk on any increase in costs that may occur in relation to other transport infrastructure over and above what is already planned.


Lambeth Cabinet on 4 March

A paper is being heard by the Cabinet on 4 March. The recommendations are:
  •  that the noise level resulting from trains does not exceed 35dB (fast) and that mitigation measures are explored to reduce the noise level as far as  possible below that level 
  • that the Council is satisfied that all other impacts of the NLE are minimised  and that this is clearly set out and demonstrated by the documents included in the Transport Works Act Order submission
  • that the shafts and any associated buildings at Kennington Green and Kennington Park are designed to the highest standard, to be determined by the Council, and that mitigation measures to minimise the impacts of noise and air pollution are provided 
  • that the proposed station at Nine Elms and the public realm surrounding it are designed to the highest quality, to be determined by the Council
  • agreement between the Council and TfL on a satisfactory package of other strategic transport improvements, including improved/new bus services, that ensures the NLE is part of an overall strategic transport solution for the VNEB Opportunity Area 
  • that the transformational change to the public realm and the bus station be progressed leading to the creation of a new district centre and the removal of the Vauxhall Gyratory wherever possible and to the satisfaction of the Council.
  • That the Enterprise Zone as it relates to Lambeth is limited to the developments know as Vauxhall Square (Planning Ref 11/04428/FUL) and the redevelopment of the existing Sainsbury store  on Wandsworth Road, (Planning Ref 11/02326OUT), as defined by the relevant planning permissions that the Planning Application Committee have approved, subject to S106 Agreements.
  • That all efforts be made to reduce the potential infrastructure funding gap by working with existing strategic partners who have a responsibility to provide infrastructure for the new population.


Benefits for Lambeth

  • 3,500 new homes and 8,000 new jobs created in Lambeth. Many thousands more jobs on the Wandsworth side available for Lambeth residents to apply for.
  • A new tube station at Nine Elms which will dramatically improve transport connections around Wandsworth Road.
  • Pressure taken off Vauxhall tube station, as passengers in Nine Elms and Battersea will not add to the demands on Vauxhall and the Victoria line.
  • A fast, direct new tube connection from Kennington to the jobs, shops and services being developed at Battersea Power Station.
  • As new buildings are erected, developers will have to pay £46m to Lambeth. Only £7.3m of that extra money will go to the Northern line. The rest will go to other projects in Lambeth, such as the sorting out the Vauxhall Gyratory System.
  • With all the new businesses in the area Lambeth will get more income from the business rates. Lambeth will keep all this extra money.
  • Only Sainsbury’s on Wandsworth Road and the Vauxhall Square development will be in the new Enterprise Zone, meaning Lambeth will give 70% of the extra business rates to Government.


Lambeth’s Overview & Scrutiny committee on 20 March

The committee that Stephen and Mark are both members of will consider the regeneration of Vauxhall and the Northern Line Extension. It is a public meeting so you are welcome to attend. We will also be holding the meeting at the Wheatsheaf Hall, South Lambeth Road, SW8 2UP, in order to hopefully make it easier for those residents most affected to get to.


Our view

Transport experts believe that the Northern Line Extension is the best way to improve transport links and regenerate the Vauxhall- Nine Elms- Battersea riverfront. No other transport solution will provide the capacity that will be needed to make the area a success.

It will cost money, but we think out of a budget of £1bn, asking Lambeth to pay £7.3m from the money developers give us and 70% of the extra business rates that businesses give us on only two sites is a great deal!

Some groups who are against the Northern line Extension will tell you that this money could be better spent on Lambeth residents and not on the Northern Line Extension. But just think about this for a minute. Without the Northern Line Extension, Battersea Power Station would not be developed. A lot of other sites in the area would not be developed, as transport will be overwhelmed. We would not get the all of the £46m from developers in Vauxhall, as there would not be a comprehensive transport solution to support all of the planned development. We would not get all of the extra business rates from the new businesses. We would not get all of the 3,500 new homes and 8,000 new jobs.

So being against the Northern Line Extension does not mean saving Lambeth £7.3m. It means costing us millions of pounds, thousands of homes, thousands of jobs and a once in a lifetime opportunity to redevelop Vauxhall- Nine Elms- Battersea.

Saturday, 12 January 2013

TfL meetings about Northern Line Extension's effects on Kennington Park and Kennington Green


Meeting to discuss design considerations for the proposed permanent shaft at Kennington Park

This meeting with representatives from TfL, Lambeth and Southwark councils, local community groups and Friends of Kennington Park will discuss the design of the proposed permanent shaft building (head house) at Kennington Park for the proposed Northern line extension.  The meeting will also be attended by TfL’s heritage and urban design leads and John MCaslan & Partners, the architects commissioned by TfL to design the above ground structures for the proposed extension.

The meeting will take place on Wednesday 16 January at St Agnes Church Hall, St Agnes Place, Kennington from 6:30 – 8pm.

The feedback from the NLE consultation about the design of the proposed head house at Kennington Park will be shared and there will be discussion of further design considerations before TfL progress with more detailed plans ready for submission as part of their application for a Transport and Works Act Order.

This is a follow up to a meeting held at the Café in Kennington Park back in October, where initial ideas shaped the indicative designs for the head house currently being consulted upon.

Please confirm your attendance by emailing nle@tfl.gov.uk


Meeting to discuss plans for the reinstatement of Kennington Green

This meeting with TfL’s heritage and urban planning leads and Lambeth’s parks and conservation officers about plans to reinstate Kennington Green once the proposed construction works for the Northern line extension (NLE) are completed.

The meeting will take place on Thursday 17  January – at the Durning Library, 167 Kennington Lane, SE11,  from 6:30 – 8pm.

Feedback from the recent NLE consultation will be shared and there will be discussion of design considerations for the reinstatement of the green further before TfL progress with detailed plans for submission as part of their application for a Transport and Works Act Order.

This is a follow up to the meeting held at St Anselm’s Church in October, where initial ideas for the reinstatement of the green shaped the indicative designs consulted upon in the NLE consultation.

Please confirm your attendance by emailing nle@tfl.gov.uk

Tuesday, 20 November 2012

Follow up Northern Line Extension meeting


Lambeth Council held a public meeting on the 10 September where residents  were invited to raise any queries or concerns they had related to the proposed extension to the Northern Line. At that meeting officers undertook to take those comments away and investigate them further and to provide answers once they had them.

Lambeth officers and the council’s technical consultant Ramboll have been working through the issues raised and are proposing a follow-up meeting to give an update on where they are and allow residents to engage in discussion on outstanding issues. The meeting will be from 6pm – 9pm on Tuesday 4 December in the South Lambeth Library, 180 South Lambeth Road, SW8 1QP. An agenda will be circulated prior to the meeting and it is likely that it will take the same format as the September meeting with each different area dealt with in turn.

You do not need to register to attend this meeting but to help estimate numbers in advance it would be useful if you could email transportplanning@lambeth.gov.uk to indicate whether you will be attending.

Ramboll's work and the meeting are focused on some of the practical issues around the construction and operation of the project. However, some residents have been questioning whether the Northern Line Extension is the best transport option to be pursuing. Lambeth officers have provided the following briefing explaining some of the reasons why TfL is pursuing the Northern Line Extension:



Reason for Choice of the Northern Line Extension

The NLE has been identified by TfL as the only viable option that will provide enough public transport capacity in the long term to accommodate the scale of development proposed for the VNEB Opportunity Area. This note explains the rationale behind this decision.

Background

Five development scenarios were initially investigated for the VNEB Opportunity Area ranging from low levels of development to significant increases in jobs and residents. A transport study was commissioned by TfL in order to identify the level of public transport provision that would be required to support the amount of development proposed for each of these scenarios.

This transport study identified a range of public transport improvements that would be required ranging from a series of bus based improvements for the low level scenarios to proposals that provided significant amounts of additional capacity for the high level scenarios.

It was eventually decided that a revision of Scenario 5 with 16,000 new dwellings and 24,000 new jobs would be pursued. The transport study had identified that the only 2 interventions that would provide enough capacity to accommodate this level of development were tube or tram-based options. These would provide direct, high speed connections to central London with much more capacity than could be accommodated by additional bus routes. Without this route the public transport system would be unlikely to cope with the additional demand.

Tube based option

The tube based option forms an extension to the Northern Line from Kennington. This is the easiest option to deliver because of the terminating tracks on the Charing Cross branch which allow an extension to be delivered without directly affecting the rest of the line.

Four initial route options were proposed. These were:

1. A direct line from Battersea to Kennington,
2. A mid-station at Vauxhall to allow interchange with the Victoria Line,
3. A station close to the proposed US Embassy, and
4. A station on Wandsworth Road (Sainsbury’s).

The first two options were discounted by TfL as not providing effective relief for Vauxhall station to accommodate significant levels of additional trips relating to developments at the northern end of the OA such as New Covent Garden Market, Sainsbury’s, CLS, etc.

In particular, although the second option would have provided interchange between the Northern and Victoria Lines TfL has always raised significant concerns that Vauxhall station would be unable to cope with additional numbers of passengers. This relates both to those entering the station to use the Northern Line at peak times leading further congestion within the station, and those interchanging onto the Victoria Line which would be likely to have implications for capacity before trains reach the more strategic part of the line at Victoria. For this reason, TfL has never supported this option.

Of the remaining options, that which provides most benefit for Lambeth residents is the 4th option with a station at Wandsworth Road (Sainsbury’s). This option provides the best improvements to public transport accessibility levels in Lambeth compared to the US Embassy option which would have been on the western side of the railway viaduct. This was also the most supported option in the public consultations that were undertaken in 2010 and 2011.

The possibility of creating a branch from the Victoria Line was considered but dismissed due to operating concerns. The Victoria Line is congested north of Vauxhall in the morning peak and the addition of additional passengers would lead to capacity problems on more strategic parts of the line further north from Vauxhall. The existing service to Brixton would have been affected by the loss of services as the trains would have had to alternate between Brixton and Battersea.

Tram based option

The tram-based option was originally devised as a connection from Battersea Power Station along Nine Elms Lane to Vauxhall, Albert Embankment and Waterloo where it would connect with the Cross River Tram (CRT). The CRT was, however, dropped from the TfL business plan following the Mayoral election in 2008.

The two main reasons why this is not supported by TfL are:

1. Impact on Vauxhall gyratory.

The tram route was proposed to run through the gyratory which is already operating close to capacity and the impact on traffic flow was deemed unacceptable by TfL. One of the Council’s key aims is the removal of the gyratory, with significant improvement to the public realm, and officers are currently in discussions regarding this. It is unlikely that a tram route could be accommodated in these proposals due to the impact on capacity. It is likely that the provision of a tram route would compromise the Council’s aim.

2. Interchange implications.

The tram was proposed to connect with the CRT at Waterloo which would have provided a direct route into central London without the need to change at Waterloo.  Without the CRT, all those using the tram would arrive at Waterloo and need to change to alternative modes of transport. Waterloo is the busiest station in London and there are already issues relating to interchange from train to tube and bus. For example, there are currently long queues for buses at peak times and it is likely that the interchange could not cope with the additional passengers.

TfL also raised concerns about potential interchange implications at Vauxhall station, with a potential increase in passengers looking to change to the Victoria Line.

Other Public Transport Improvements

The transport study identified that either a tube or tram based option would be the only solutions to provide the long term public transport capacity required to accommodate additional development trips. However, the Council has always stated that a wider transport strategy, with a significant emphasis on bus improvements, is required and that this would link the new developments to existing residents and businesses in Lambeth. Such improvements formed a key part of the Council’s initial support for the NLE.

The VNEB transport study showed that bus improvements would be required in the short to medium term, until the high capacity improvements were constructed. Given the number of developments that have now obtained planning permission TfL is currently undertaking an initial study into short term bus improvements and the Council will feed into this study to ensure that the proposals provide the required level of improvements to Lambeth residents.

Issues raised on the NLE

The Council has received a lot of correspondence from residents regarding the NLE. In order to be able to respond to these issues and ensure that TFL, as scheme promoter, takes them on board the Council has engaged consultants Ramboll to act on its behalf and provide advice. At present Ramboll are reviewing the work done to date on behalf of Treasury Holdings and latterly TfL. It is hoped that they will continue to advise the Council on the Environmental Impact Assessment that TFL is required to submit in support of the Transport and Works Act application.

Conclusion

The need for the NLE is development led, with significant additional transport capacity being required to accommodate the additional trips that will be generated by all developments in the VNEB OA. The Planning Framework concludes that in order to enable and support a revised scenario 5 development a package of strategic transport measures, supported by a series of more local transport improvements will be required to support growth and development of the OA. These include:

• An optimum package of bus service enhancements including the introduction or extension of bus routes
• An extension to the Northern -Line, from Kennington to Battersea Power Station, with an intermediate stop in the Nine Elms area
• Improvements to the National Rail, Underground stations and interchange facilities at Vauxhall and Battersea Park stations
• A step change in the walking and cycle environment both within and to/from the OA and ensuring improved legibility and connections
• An approach to development which reduces the need to travel by car/reduces the number of private vehicle trips within the OA
• Improving conditions for taxis, coaches, freight and river services within and to/from the OA
• Private investment to enable these improvements to be secured and delivered in line with the future development of the area

It can be seen, therefore, that the NLE is not the only transport improvement that will be delivered. The Council has always supported and promoted additional bus enhancements in the area that will be of benefit to Lambeth residents.


Monday, 10 September 2012

Council listening to residents' Northern Line Extension concerns

Lambeth Council have appointed tunnelling experts Ramboll as independent technical consultants to examine Transport for London's plans for the Northern Line Extension, which are are progressing quickly.

At an exhaustive three hour meeting this evening, chaired by London Assembly Member Val Shawcross, experts from Ramboll listened to the detailed concerns that residents have about the construction and operation of the Northern Line Extension.

Issues included:
- the exact location of the construction shaft in Radcot Street (not yet decided)
- the effect on adjacent properties
- air quality next to the shaft
- parking during construction (the gin distillery was suggested as a possible site for parking)
- traffic circulation through 'Methravia' during construction
- size and quality of the construction vehicles
- hours of construction work
- noise - construction of tunnels and operation of the trains
- capacity of Kennington station - for additional trains and additional passenger interchange
- boundary issues - discussions with Southwark
- process for monitoring any settlement or damage caused by tunnelling
- the need for maximum noise mitigation around the 'Kennington Loop' - where the NLE will meet the existing track and be at its most shallow - and the need for the existing track on the Loop to be upgraded to reduce noise disruption.
- how to manage Kennington Park during construction, reproviding the dog exercise area and ensuring community projects aren't forced to close.
- which shaft site has been decided for Kennington Green - the distillery is preferred and residents want the trees protected
- the proposed permanent shaft at Claylands Green which is fiercely opposed by local residents there and TfL are now examining whether other options are possible.
- what noise and effect the permanent ventilation shafts will have.

There was a clear consensus from residents and councillors that
- Lambeth Council must demand the minimal construction disruption to residents possible.
- Lambeth Council must insist on the highest possible noise mitigation work for the operation of the trains.
- Lambeth Council must specify construction techniques which are least noisy and least disruptive to residents.
- Ramboll need to examine TfL's plans in great detail and not be afraid to challenge them to improve the project's effects on Lambeth's residents.

Councillor Mark Harrison said 'the meeting was a really useful and detailed airing of all the many concerns that Lambeth residents have about the Northern Line Extension. Now independent experts Ramboll can go away and examine TfL's plans in detail and get answers to the questions raised'.



Monday, 20 August 2012

Northern Line Extension residents' meeting


Plans for the Northern Line Extension are progressing quickly.

In order to ensure that Lambeth Council secures the best possible outcome from the NLE and minimises any negative impact on residents and businesses both during the construction phase and once it is operational the Council has appointed technical consultants. Ramboll have extensive experience on major tunnelling projects including Crossrail and will advise on all issues related to both design and implementation.

Ramboll are undertaking a review of the design work completed up to this point by TfL and Lambeth Council has asked them to give particular consideration to some key areas such as noise and vibration, shaft locations and construction methodology.

To ensure that Ramboll are able to concentrate on the right areas the Council has organised a meeting with residents and resident groups on Monday 10 September in the Ashmole Tenant’s Hall, Meadow Road, SW8 1AA.

As the NLE route covers a large area and spans three Wards it is proposed that the agenda of the meeting would be divided geographically between Prince’s, Oval and Stockwell allowing people to come and go for the parts that concern them.  It will run from 6pm to 9pm with roughly an hour given to each Ward with Prince’s dealt with first followed by Oval and then Stockwell. Prince's ward issues will be dealt with between 6pm and 7pm. An agenda will be circulated in advance of the meeting giving the exact timings and these will be based on the relative interest shown for each area.  Please note that TfL have not been invited to this meeting.

Please bear in mind that this meeting will have a clear focus on detailed issues such as noise and vibration, shaft locations and construction methodology - not the overall principle of whether or not to go ahead with the NLE.

If you would like to attend this meeting please email William Howe.

Friday, 6 July 2012

Northern Line Extension Update


Transport for London have updated us on plans for the extension of the Northern Line, from Kennington to Battersea.

The main benefit of the NLE is that it will provide the necessary transport capacity for Battersea Power Station to be fully redeveloped. It will also provide a new station at Nine Elms (next to Sainsbury) which will take pressure off Vauxhall tube station.

The developer of Battersea Power Station had been leading the NLE project, but they went into administration at the end of last year, so TfL confirmed its intention to take forward the Northern line extension project to Transport Works Act Order (TWAO) stage. This is the legislation needed to start work on a major transport project.

A preferred bidder has been chosen for the development of the Battersea Power station site and TfL will be working with them to take forward plans for a proposed extension of the Northern Line.

The wider work necessary in advance of submitting a TWAO continues and this week TfL are updating residents and stakeholders on the progress of their plans. Over 40,000 households and businesses along the route of the proposed extension will receive a leaflet. This will be followed by further local consultations to refine some of the details of the scheme over the coming months with a final consultation on proposals planned for the Autumn.

To construct the NLE there will need to be a temporary construction shaft in the Radcot/ Stannary Street area, and permanent ventilation shafts on Kennington Green and Kennington Park. You can find out more, and view a detailed map of the plans, on TfL's website.


Tuesday, 17 May 2011

VNEB Community Forum



Yesterday evening saw a second well-attended Lambeth Community Forum for the Vauxhall-Nine Elms- Battersea project.



The Forum is the place for Lambeth community groups and residents to engage with the work of the VNEB Strategy Board, which is coordinating the redevelopment of the area stretching from Lambeth Bridge to Battersea Bridge.



Cllr Steve Reed, Leader of Lambeth Council, introduced the event. He is now representing Lambeth on the Strategy Board, ensuring the Lambeth point of view is represented as strongly as possible.



There was a presentation on the proposed extension to the Northern Line. A consultation is underway - events will be held for residents at the following times:
- Friday 20 and Saturday 21 May from 10am to 6pm at The Long Room, The
Oval, SE11 5SS
- Thursday 26 and Friday 27 May from 10am to 6pm at Sainsbury’s Nine Elms,
62 Wandsworth Road, SW8 2LF
The discussion about the Northern Line Extension was lively. The biggest concern is that money from new Lambeth developments will be siphoned off into the NLE, instead of paying for vital infrastructure needed at Vauxhall Cross. Councillors present confirmed they were well aware of this issue and were continuing to press Lambeth's case in negotiations.